What is the Difference Between Process Review and Manufacturing Feasibility Review? — Four Questions, Five Dimensions, and a 20-Item Checklist Before the Drawing Goes to the Shop Floor
One Sentence to Distinguish: One Decides Whether to "Accept the Order," the Other Decides Whether the "Drawing Can Go to the Shop Floor"
These two terms are often mixed up in design review meetings, but their timing, participants, and outputs are entirely different:
- Manufacturing Feasibility Review occurs before quoting: Can this production line, this set of equipment, and this team do it? Should we quote? How much should we quote? The output is "order acceptance decision + risk and cost assumptions."
- Process Review (also known as Design Process Review) occurs before the drawing is finalized and production begins: Can every feature on the drawing be stably produced, easily measured, and easily assembled with the current process in the shop floor? The output is "drawing modification suggestions + closed-loop disposal."
The former is a business and capability assessment, while the latter is a technical review. The former asks "Can we do it?" and the latter asks "Is this drawing feasible?"
| Dimension | Manufacturing Feasibility Review | Process Review |
|---|---|---|
| Timing | Before quoting, order acceptance review | Before drawing finalization, before trial production, during design changes |
| Leading Department | Sales/Project + Process + Quality | Process department leads, design department assists |
| Input | Customer requirements, initial drawing, production capacity load | Drawing (including tolerances and technical conditions), material list, sample requirements |
| Output | Order acceptance decision, cost and cycle commitment, risk list | Review suggestion form (mandatory, recommended, accepted), drawing revision |
| Cost of Failure | Accepting an order that cannot be fulfilled, losing money and reputation | Producing with a problematic drawing, leading to scrap, rework, and delays |
| Signatories | Project leader + plant level | Process supervisor + design supervisor (double signature) |
Many factories only conduct the former and not the latter—calculating very carefully when accepting orders, but "directly processing" the drawings once they arrive. The result is that all the issues on the drawings become rework orders in the shop floor.
Four Key Questions for On-Site Review
The items for process review can be listed in dozens, but the four key questions used in on-site reviews correspond to four dimensions. If any one of these questions cannot be answered, the drawing should not be released:
- Can it be made?—Processability. Structure, wall thickness, depth-to-width ratio, minimum hole diameter/fillet radius, tool/electrode reachability, clamping datum.
- How accurately can it be made?—Measurability. Tolerances and datum, dimension chain, whether inspection tools and methods are reachable, how to inspect key characteristics.
- Is it stable?—Stability. Process capability (Cpk), deformation and thermal effects, fixture rigidity, batch consistency, yield estimation.
- Is it cost-effective?—Economic feasibility. Material utilization rate, number of processes and cycle time, tooling and mold investment, rework and scrap costs.
These four questions are a condensed mnemonic for on-site use—first ask "can it be done?" (1, 2), then ask "is it stable and cost-effective?" (3, 4). The order cannot be reversed: if it cannot be made, discussing stability and cost is meaningless.
| Four Questions | Corresponding Dimension | Typical Criteria | Recording Method |
|---|---|---|---|
| Can it be made? | Processability | Minimum wall thickness, depth-to-width ratio ≤ 3, internal corner radius ≥ tool/electrode radius, reachability | Drawing annotations + process plan |
| How accurately can it be made? | Measurability | Whether tolerances can be covered by inspection tools, unique datum, closed dimension chain | Inspection plan (including inspection tool list) |
| Is it stable? | Stability | Key characteristic Cpk ≥ 1.33, controllable deformation, fixture repeat positioning ≤ 1/5 tolerance | Preliminary process capability assessment |
| Is it cost-effective? | Economic feasibility | Material utilization rate, number of processes and cycle time, tooling investment payback period | Cost comparison table |
Five Dimensions and a Directly Usable Checklist
Review is not just "glancing at the drawing and thinking it's fine," but a detailed item-by-item check. The following checklist is organized by five dimensions and can be directly pasted into the review record form:
Dimension One: Structure and Processability
- Is the minimum wall thickness within the conventional range of the selected process (injection molding, die casting, machining each have different ranges)?
- Is the internal corner radius ≥ the tool/electrode radius? Are there any "square fillets" that cannot be processed?
- Is the depth-to-width ratio of deep holes, deep grooves, and narrow slots greater than 3:1? If so, how will tool rigidity, chip removal, and cooling be handled?
- Are there any hidden areas that tools, grinding wheels, or welding torches cannot reach? Is special tooling required or should the structure be modified?
- Are unconventional standards used for features such as threads, splines, and tooth profiles? Can suppliers meet these requirements?
Dimension Two: Materials and Heat Treatment
- Is the material grade unique, and are there any alternative grades? Are the procurement cycle and minimum order quantity acceptable?
- Do the heat treatment/surface treatment requirements match the material (e.g., certain steel grades may deform uncontrollably after nitriding)?
- Are welding methods, joint types, and inspection requirements specified for welding structures? Are there transition solutions for welding dissimilar materials?
- Does the choice of raw material (bar stock, forging, casting, profile) match the batch size? Using castings for small batches may result in mold costs.
Dimension Three: Tolerances, Datum, and Dimension Chain
- Is the datum unique and consistent with the assembly datum and inspection datum? Conflicts among the three datums are the primary cause of dimension chain over-tolerance.
- Are tolerances annotated in layers? Is the entire drawing annotated with ±0.01 (treating process capability lightly)?
- Do key dimensions form a closed dimension chain? Are there any over-constraints (providing redundant constraints can make production impossible)?
- Are the selected items for form and position tolerances reasonable (e.g., which is cheaper to measure, concentricity or circular runout)?
Dimension Four: Assembly and Usage
- Is the assembly sequence feasible? Are there any interferences that prevent assembly (bolt head space, tool rotation radius)?
- Is the poka-yoke design adequate—do left/right parts, front/back parts, and similar parts have physical anti-error features (see the poka-yoke topic in this column)?
- Is special assembly tooling required? Is the tooling investment included in the cost?
Dimension Five: Inspection and Packaging
- Is there an executable inspection method for each key characteristic? Are the inspection tools self-made, purchased, or coordinate measuring machines (CMM)?
- For non-destructive testing (NDT) requirements, are the methods (UT/RT/MT/PT) and acceptance levels clearly specified? Who is qualified to perform the tests?
- Do the testing and validation requirements (airtightness, fatigue, salt spray) match the actual usage environment of the product?
- Are the packaging, labeling, and traceability requirements clearly defined (how to mark batch numbers, traceability to which level)?
These 20 items do not need to be reviewed in full every time—they should be tailored to the product type, with the reasons for tailoring documented.
How to Organize a Review: Three Triggers, Four Categories of Participants, Three Conclusions
Triggers (missing any one will result in omissions):
- Before design freeze (DR stage gate), when the new version of the drawing is first issued;
- Any design change (including material substitution, supplier change);
- Before small batch trial production (before the first article, no later than before PPAP).
Participants: Process (chair), Design (response), Quality (inspection feasibility), Manufacturing/Shop Floor (clamping and cycle time). If necessary, key suppliers should be involved. A process review without shop floor personnel present is likely to miss clamping issues.
Only three types of conclusions are allowed, no "almost":
| Conclusion | Meaning | Disposition |
|---|---|---|
| Mandatory | Cannot be made, unstable, or unmeasurable without modification | Re-review the drawing after revision, do not release until modified |
| Recommended | Can be made, but with significant cost or yield disadvantages | Design confirmation; rejection must be documented |
| Accept and Record | Feasible under current conditions, risks identified | Risks entered into PFMEA, control measures into the control plan |
The last point is often overlooked: "accept" does not mean "no problem," but "aware of the risks and have implemented control measures in documents and on-site". The review suggestion form should be traceable to the PFMEA row number and key characteristic number; otherwise, the form is just a formality.
How to Connect with Other System Links
Process review is not an isolated action; it is naturally a convergence point for several chains:
- Forward to DFM/Design for Manufacturability (moving manufacturing constraints to the design stage, see "Practical DFM Design for Manufacturability");
- Lateral to Special Characteristics (key dimensions identified in the review should be upgraded to special characteristics and included in the drawing specifications and control plan);
- Downward to PFMEA and Control Plan (each "accept and record" risk must have a failure mode and detection method);
- Further downward to First Article Inspection (review conclusions must be verified on the first article, not just on paper);
- During changes to Design and Process Change Management (drawing revision, breakpoints, inventory switching, none can be missed).
Six Common Pitfalls
- Confusing "Can Be Made" with "Can Be Stably Made"—The sample looks great, but the batch yield is 70%. The review must ask about process capability, not just the sample.
- Reviewing Only Structure, Not Inspection—No matter how strict the tolerances are, if the factory cannot measure them, they are meaningless.
- Highest Precision for the Entire Drawing—Designers use "a bit stricter for safety," but this actually doubles the cost and increases the rework rate; tolerances should be layered by function.
- Review Meetings Without Documentation—Oral agreement that "this corner can be made square" is forgotten three months later.
- Supplier Side Only Looks at Quotation—The process review for outsourced parts should follow the order, especially for castings, forgings, and surface treatments.
- Changes Not Re-reviewed—Material substitution, supplier change, mold modification, any change requires re-running the four questions.
The defense and aviation industries have standardized this process: the aerospace industry has QJ 1885 "Process Review of Aerospace Product Design Documents," and the aviation industry has HB/Z 99.3 "Regulations for Process Review Work" and HB/Z 227.3 "Process Review of Product Design." The common points are—checklist for review content, written review opinions, double signature by design and process, no release until closed-loop. Civil product enterprises do not need to copy the standard clauses, but these three organizational principles can be directly applied.
One Sentence to Conclude
The manufacturing feasibility review decides whether to "accept the order," while the process review decides whether the "drawing can go to the shop floor." The former relies on capacity and cost assessments, while the latter relies on the four questions—can it be made, how accurately can it be made, is it stable, is it cost-effective—item by item, documenting "mandatory, recommended, accepted and recorded," and then pinning the accepted risks into the PFMEA and control plan. Only then does the drawing qualify to become a process card.